The Pipeline Project




The Memorandum of Understanding defining the main principles of the Yadana project was signed in July 1992. Gas production began on schedule in July 1998, and commercial production followed in 2000. The period of six to eight years that elapsed between the initial commitment and full production illustrates the length and complexity of the process of developing oil and gas fields.


In 1992 and 1993, the project focused on determining whether the field, which had not been fully appraised, contained sufficient gas reserves to warrant the US$1-billion investment required to bring it on stream and transport the gas.

Complex geophysical surveys had to be conducted and appraisal wells drilled. At end-1993, sizeable reserves were confirmed and the technical processes for bringing the field on stream were defined in greater detail.

The other indispensable requirement before proceeding was finding a profitable, long-term market for the gas. Unlike oil, which is easy to transport, and a few rare giant gas fields that are big enough to warrant the construction of a multi-billion-dollar liquefaction plant that offers greater flexibility for finding long-term custormers, natural gas is sold in the pipe. The negotiations with the logical purchaser of Yadana gas, Thailand's PTT, took place from February 1993 to February 1995.

Laying the pipeline on uneven terrain
During the exploration and commercial negotiation period, Total's specialized departments prepared the technical development plan to serve as a basis for talks with equipment suppliers and other subcontractors.

February 1995 was the real starting point for operations. The offshore partners and shareholders of MGTC agreed on the Yadana field development plan, the gas sales and purchase contract with PTT was signed, and a final decision was made on the onshore pipeline route. Construction work could begin.

Nature had a large say in the work. Eight meters of water fall in the region during the annual monsoon season between May and September, making work impossible. Construction was therefore divided into three phases, each running from October to May.

Detailed field surveys began in late 1994 and continued into 1995.
The project infrastructure was built during the first season, from October 1995 to May 1996. It included wharf facilities in the Heinze Chaung River estuary so that equipment could be shipped in from Singapore, an airfield, landing pads for helicopters, roads, bridges and temporary buildings to house the teams and manage the site.
The 63 kilometers of onshore pipeline to the Thai border were laid between October 1996 and May 1997.
The project was completed between October 1997 and May 1998 with the construction of the two operating management centers for the structure, the pipeline center near Kanbauk and a metering station for the gas delivered to the border at Ban I Tong. A service road was built so that the pipeline could be maintained, and the vegetation was restored so that there was no lasting impression on the environment.
The offshore facilities were built at the same time. This comprised installation of the platforms, built in Singapore, and the laying of 346 kilometers of subsea pipeline. The project was completed on schedule on July 1, 1998. Commercial commissioning took place in early 2000, since the economic turmoil in Asia had delayed the construction of the Thai power plants to be fuelled by the gas.